ERW straight seam resistance welded pipe and JCOE LSAW (longitudinal submerged arc welded) pipe manufactured by Cangzhou Jinyang Pipeline Manufacturing Co., Ltd. for fluid conveyance and structural projects....
1) For small and medium diameters at normal pressure, ERW is usually the more economical and faster option; 2) For high-pressure oil and gas trunk lines, crossings and structural work above DN400, specify JCOE, with PSL2 where required; 3) Confirm the base-pipe standard and surface preparation before galvanizing, coating or anti-corrosion; 4) State OD, wall thickness, steel grade, length, end finish and inspection items on the order.
| Parameter | ERW HF welded pipe | JCOE LSAW pipe |
|---|---|---|
| Size | DN15–DN600 (Φ21.3–Φ630 mm) | DN400–DN1400 (Φ406–Φ1422 mm) |
| Wall thickness | 1.8–16 mm | 8–30 mm |
| Standards | GB/T 3091, API 5L, ASTM A53/A135, EN 10219 | GB/T 9711, API 5L (PSL1/PSL2) |
| Typical use | Water, gas, fire protection, scaffolding, steel structures | High-pressure oil and gas trunk lines, crossings, structural works |
Straight-seam welded pipe is produced in two ways. ERW pipe joins the strip edges with high-frequency resistance heating, leaving a single longitudinal weld. It is common for small and medium diameters, with good dimensional accuracy and wall uniformity, and suits water, gas, fire protection and structural duties in stable batch volumes.
JCOE pipe starts from steel plate, which is formed, tack welded, submerged-arc welded inside and out, then expanded and sized as required. It covers larger diameters and longer single lengths and is widely used for large-diameter pipelines and structural work. Whether it meets high-pressure or long-distance requirements must be confirmed against the design documents, the applicable standard and the inspection requirements.
Both types can be supplied with end preparation (plain, bevelled, flanged or coupled), external protection (3PE, epoxy, galvanizing) and internal lining, with dimensional and weld checks performed per batch before shipment. Where NDT, hydrostatic testing or third-party witnessing is required, please state it at the enquiry stage.